# Sprint plan with progress

> Two weeks of tasks, each bar filled to show how much is done, and a line for today. A pgfgantt example with its LaTeX source.

A pgfgantt example in the TeXeR TikZ library: https://texer.org/library/pgfgantt/gantt-progress

Package: [pgfgantt](https://texer.org/library/pgfgantt.md), on CTAN at https://ctan.org/pkg/pgfgantt.

Tags: gantt, sprint, progress

## Source

```latex
\usepackage{pgfgantt}

\begin{ganttchart}[
  hgrid, vgrid={*6{draw=none}, *1{dotted}},
  x unit=5mm, y unit chart=6mm, y unit title=6mm, title height=1,
  title label font=\small, bar label font=\small,
  today=7, today label=Today, today label font=\small,
  bar/.append style={fill=green!45!black},
  bar incomplete/.append style={fill=gray!20},
]{1}{14}
  \gantttitle{Sprint 12}{14} \\
  \gantttitlelist{1,...,14}{1} \\
  \ganttbar[progress=100]{Design review}{1}{3} \\
  \ganttbar[progress=60]{API endpoints}{3}{8} \\
  \ganttbar[progress=20]{Front end}{6}{12} \\
  \ganttbar[progress=0]{Release notes}{12}{14}
\end{ganttchart}
```

## As a complete document

The same example in a document that compiles on its own with pdfLaTeX:

```latex
\documentclass[margin=3mm]{standalone}
\usepackage{tikz}
\usepackage{xcolor}
\usepackage{amsmath}
\usepackage{amssymb}
\usepackage{pgfgantt}

\begin{document}

\begin{ganttchart}[
  hgrid, vgrid={*6{draw=none}, *1{dotted}},
  x unit=5mm, y unit chart=6mm, y unit title=6mm, title height=1,
  title label font=\small, bar label font=\small,
  today=7, today label=Today, today label font=\small,
  bar/.append style={fill=green!45!black},
  bar incomplete/.append style={fill=gray!20},
]{1}{14}
  \gantttitle{Sprint 12}{14} \\
  \gantttitlelist{1,...,14}{1} \\
  \ganttbar[progress=100]{Design review}{1}{3} \\
  \ganttbar[progress=60]{API endpoints}{3}{8} \\
  \ganttbar[progress=20]{Front end}{6}{12} \\
  \ganttbar[progress=0]{Release notes}{12}{14}
\end{ganttchart}
\end{document}
```